Structure statics are based on the loads in the project. You do not have to retype them: a fixture hung under a truss or a screen at the bottom chord goes into the calculation automatically. You only add by hand what is not in the scene.

Structure inspectorStatics and supportLoads

Self-weight

Self-weight includes the trusses (linear mass of the series), corners and connectors. The statics calculate it as a separate load case. Manufacturer load tables give the additional load without self-weight, so span utilization is calculated from the additional load, and reactions and deflections from the total.

Automatically attached equipment

The app assigns equipment to a structure by its position in the scene:

EquipmentWhen it counts as a loadHow
Fixtures and devicesWithin 0.4 m of the run axis in plan and 0–1.5 m below the bottom chordPoint load: mass + 1 kg hardware (moving head 2.4 kg)
LED screensTop edge within 0.6 m below the bottom chord, footprint overlaps the runUniform load over the shared part: screen mass + 7 %
Loudspeakers and arraysA set with Flown mountingMass with frame at the hanging point

Assigning an object to a structure by hand takes priority over the position rule. The Attached equipment row shows how many fixtures, devices and screens hang on the structure and how much they weigh. When expanded, it shows a list with a Select button next to each item.

Fixtures: truss magnet

Fixtures from the Lighting library and sets from the Sound menu snap to a run while you drag them. The clamp sits on the bottom chord and the device hangs below it. The label next to the cursor shows the truss utilization after adding the fixture. Alt turns off the magnet, Shift turns off the 0.25 m grid. Fixture placement is described in the article Lighting on truss.

Loudspeakers and arrays

An array or a point-source loudspeaker dropped near a truss attaches to the nearest run above the point (within 3 m in plan, bottom chord at least 3 m above the floor) just below the bottom chord. The statics then count the mass of the set with its frame. A set flown away from any project structure gets a note about the required rigging point. More in the article Inserting, L/R pair and magnet.

Cables

If the cabling plan routes cables along the truss, the statics take the mass of those cables. Without routes, the app assumes an allowance in kg/m. The Cables row shows the mass and its source, for example "Allowance 2.0 kg/m (no routes along the truss in the cabling plan)". You can change the allowance in the wizard (Cable allowance) or in the Advanced → Factors section. See also the cabling plan.

Manual loads

You add set pieces, banners, flybars and other items that are not in the scene in the Advanced → Manual loads section.

  1. Click Add load.
  2. Choose the run (B1, B2…).
  3. Choose the type: Point (point load) or Run (uniform load along the whole run).
  4. Enter the mass in kg.
  5. For a point, enter the position in meters From run start.

Mass in the tiles

Total mass
Structure, equipment, cables and manual loads. The extra line shows the mass of the structure alone and the part standing on the floor (towers, bases, ballast).
On points total
Sum of the rigging point loads.
On towers total / On stands total
Sum of the loads on ground supports.
Most loaded point
The load and WLL of the point and the hoist model.
Did not find the answer?