Power connection, generator and distribution boards

How the app sizes the power connection or generator to the scene load, which distribution boards it places and what happens when you change the power connection.

4 min read
Documentation contents ▾

The power plan starts from a single source: the venue's power connection or a generator. A cable runs from it to the main distribution board, then on to sub-distribution boards near clusters of loads, and 230 V circuits run from their sockets to fixtures, screens and devices.

Sizing the power connection

The wizard and the Power tab show the scene's maximum load and the minimum power connection. The power connection is calculated from the current of the most heavily loaded phase, up to approx. 80 % of the rated current. If you choose one that is too small, the wizard shows the issue "Power connection too small" with a button that sets the minimum.

Power connectionRated currentApparent power 3-phasePlanned power per phase (80 %)
CEE 16 A16 A11.1 kVA2.94 kW
CEE 32 A32 A22.2 kVA5.89 kW
CEE 63 A63 A43.6 kVA11.6 kW
CEE 125 A125 A86.6 kVA23.0 kW
Powerlock 400 A400 A277 kVA73.6 kW

You choose the power connection location in the wizard (Power connection location → Pick, back to default with Default). Power cable lengths and voltage drop are calculated from this point.

Generator

The power connection list also includes Generator … kVA, with the rating picked automatically. Sizing method: the larger of two values, the maximum load and three times the load of the most heavily loaded phase, converted at cos φ 0.8 with the generator loaded up to 80 %, rounded up to a typical rating from the list (20, 30, 45, 60, 80, 100, 130, 150, 200, 250, 300, 400, 500 kVA). Phase imbalance therefore increases the required generator rating.

With a generator, the app raises the voltage drop thresholds by 3 percentage points (6 % warning, 8 % error by default) and assumes a higher source impedance in the fault loop check.

Distribution boards in the plan

The planner places a main distribution board matched to the power connection's connector and sub-distribution boards near clusters of loads (loads grouped on the floor plan by power). Distribution boards added by the planner get names like "Main distribution board", "Sub-distribution board", "Multipin breakout".

Distribution board from the catalogInputOutputs
Distribution board 16 A/3-phase → 3 × 230 VCEE 16 A 5-pin9 × Schuko (3 per phase)
Distribution board 32 A/3-phaseCEE 32 A 5-pin9 × Schuko, 3 × TRUE1 (C16 and 30 mA RCD per circuit)
Distribution board 63 A/3-phaseCEE 63 A 5-pin2 × CEE 32 A, 2 × CEE 16 A, 6 × 230 V
Distribution board 125 ACEE 125 A 5-pin2 × CEE 63 A, 2 × CEE 32 A, 2 × CEE 16 A
Distribution board 400 A PowerlockPowerlock2 × CEE 125 A, 2 × CEE 63 A, 2 × CEE 32 A, outgoing feeds with 300 mA type S RCD
Multipin breakout 6 × 230 VSocapex 196 × TRUE1

When more than 4 circuits run from one distribution board to the same truss, the planner routes a 6-circuit multipin with a breakout on the truss instead of separate cables.

On a full recalculation, planner distribution boards that the new plan no longer uses are removed from the scene. Distribution boards placed by hand and locked ones stay.

Changing the power connection

  1. Open the Power tab in the Cabling panel.
  2. In the Power connection group, choose a different connector or a generator.
  3. The app replaces the main distribution board with the type for the new connector and plans power again (cable from the power connection, sub-distribution boards, circuits), then runs the fix loop.
  4. Manual cables, locked cables and padlocked circuits stay unchanged.

Power connection and distribution board warnings

WarningWhen it appearsFix button
Max. load exceeds the power connectionPhase current above the planned power connection limit (approx. 80 % of rated current).Change power connection (none for Powerlock 400 A: a second source is needed)
Distribution board has too few 230 V sockets or 400 V outputsThe plan uses more sockets than the distribution board has.Add distribution board
Distribution board phase current above input currentError above 100 %, warning above the load threshold (80 % by default).Recalculate power or Balance phases
Cable fed from a larger protective deviceProtective device at the start of the cable is larger than the cable's current-carrying capacity or the distribution board's input current.Replace distribution board, Recalculate power or Show
Control room load outside the power balanceThe control room's 3-phase distribution board is fed by a cable without a circuit.Recalculate power
16 A selectivityA 16 A distribution board fed from a 16 A protective device has C16 circuits (information).none