The bill of materials comes from the same solution as the geometry and statics. When you change a run length or add a hoist, the parts list and masses update right away.
BOM groups
| Group | Contents |
|---|---|
| Trusses | Straight sections by length and series, circle arcs |
| Corners and nodes | n-way corners or box corners by angle |
| Towers and bases | Tower sections, base plates, outriggers, GS bases and heads, stands |
| Connectors | Section joints: conical couplers, pins, R-clips |
| Rigging | Slings, shackles, steels, safety cables for attached devices |
| Hoists | Hoists with class and capacity, chains |
| Ballast and guy lines | Tower ballast and guy lines outdoors, with a note on the required mass or force |
Items have a quantity, unit, unit mass and total mass. Masses are marked as indicative.
BOM for the whole project
The Bill of materials section in the panel adds up all structures in the project and the individual loose parts. The summary gives the number of structures and the total mass. The Export CSV button saves the file zestawienie-konstrukcji.csv.
BOM for one structure
The Bill of materials section in the inspector covers only the selected structure. The export icon saves a CSV file with the structure name in the file name.
CSV file format
- UTF-8 encoding, semicolon separator, decimal comma: the file opens correctly in a spreadsheet with Polish regional settings.
- The first row is a disclaimer about the nature of the values.
- Columns:
Group,Item,Manufacturer/Series,Quantity,Unit mass (kg),Total mass (kg),Notes. - The last row,
Total, adds up the mass. - Indicative items have "≈ indicative value" in the notes.
Project report
The project report has a Structures section with spans, points, warnings, the statics status and a build checklist (for example mounting equipment on the ground, setting out towers, checking ballast outdoors). Structure warnings also go into the report summary list of notes.