Outdoor: wind, ballast and guy lines

What the Outdoor setting changes: wind force on trusses, banners and screens, tower stability, required ballast or guy line force, and the warnings and fixes.

2 min readStudio plan
Documentation contents ▾

An outdoor structure must withstand the horizontal action of wind. When you set Location to Outdoor in the wizard or the inspector, the app adds the wind force and checks the towers for overturning and base sliding.

Structure inspectorStructureSupportLocation: Outdoor

What is calculated

The wind force is ½·ρ·v²·c_f·A. The app calculates it for:

  • trusses: area from the length, cross-section and solidity ratio,
  • banners, mesh and screens as boards (c_f 1.8),
  • a stage roof: the front skirt, the membrane profile and the suction over the roof area, which reduces the stabilizing load on the supports.

The default design speed is 15 m/s. Treat it as the operating speed: above it, screens and banners are lowered according to the venue procedure. For towers there is also a horizontal load from imperfections (1/200 of the vertical load).

Settings

Banners and mesh
Advanced → Wind: area in m². Also works indoors (for the wind area information).
Wind speed
Outdoors only: design speed in m/s.
Ballast per tower
Outdoors only: ballast mass in kg. The field caption shows the required minimum from the indicative calculation, or a note that ballast is not needed.
Guy lines
Structure → Support, outdoors only: the switch adds 4 guy lines per tower.

Warnings

SituationMessageFix
Outdoor without ballast or guy lines"Wind … m/s: ballast per tower min. … or 4 guy lines per tower with a force of min. …"Add … ballast per tower
Wind area"Wind area: … At … m/s this is approx. … of horizontal force."Enter banners
Stability ensuredA note with the horizontal force and what provides stability (ballast, guy lines, mass)None
Slender tower"… on a 0.6 m base plate: H/B = …"Base plate 0.8 m, Add outriggers

Ballast and guy lines go into the bill of materials in the Ballast and guy lines group. With guy lines, the note gives the minimum guy line force.

Good practice

  • Enter the real area of banners and mesh, including those on the stage fencing if they hang on the structure.
  • Agree the operating wind speed and the screen lowering procedure with the structural engineer first, then enter it in the app.
  • Check the wind forecast before the build and before lifting.
  • The wind plan, ballast and anchoring are always approved by a qualified person.